Sharjah data centre plan: 400MW Kalba free zone approved
Sharjah data centre plans take shape as the emirate approves a 285,000 sq m Kalba free zone with a 400MW complex, two power stations and six plots.

Sharjah has approved the masterplan for a technology free zone in Kalba that reserves land for a data centre complex with a target capacity of 400MW, state news agency WAM reported on 20 November. The Sharjah data centre plan places the emirate alongside Abu Dhabi, Dubai and Riyadh in a regional push to build computing capacity for artificial intelligence.
Sheikh Sultan bin Ahmed Al Qasimi, Deputy Ruler of Sharjah and Chairman of the Sharjah Communication Technologies Authority (SCTA), approved the plan for the Sharjah Communication Technologies Free Zone, according to the WAM report. The zone is intended to attract global technology companies, specialist talent and investment in technology, AI and data centres, and to help diversify the emirate’s economy.
What the Kalba free zone masterplan includes
The site covers 285,000 square metres on Sharjah’s east coast, about three kilometres from the Gulf of Oman and connected to the Kalba Ring Road. Six plots are set aside for data centres and can be combined to host larger projects, giving developers and operators room to grow in line with their own expansion plans.
The masterplan also allocates dedicated sites for two power stations to serve the data centres, together with land for telecommunications networks, water and other support services. A business centre will handle company registration and commercial licensing for approved activities, alongside a gateway building, office and administrative buildings, open spaces and pedestrian paths.
The 400MW data centre complex is a planned total rather than existing capacity. No developer, operator, investment value or construction timeline has been announced.
Background: a free zone built for data
The free zone was created by an Emiri decree issued by the Ruler of Sharjah, Dr Sheikh Sultan bin Muhammad Al Qasimi, on 1 July 2024, weeks after the SCTA itself was set up. The decree gave the zone, known in English as COMTECH, financial and administrative independence under the authority.
Under the decree, companies, institutions, individuals and employees in the zone are exempt from taxes imposed in the emirate on their activities within it for a renewable period of 50 years, and the zone is exempt from local taxes and fees other than consumption duties, Gulf News reported at the time.
In 2024 the SCTA also signed a memorandum of understanding with Khaznah Sharjah, a joint venture between BEEAH Group and Khazna Data Centers, to develop Tier-3 data centres in Sharjah, including a facility in Kalba. The masterplan announcement does not say whether that partnership will take any of the new plots.
Why the Sharjah data centre push matters
The UAE and Saudi Arabia have committed billions of dollars to data centres as the two countries compete to host AI computing capacity, AGBI noted in its report on the plan. Projects announced so far have clustered in Abu Dhabi, Dubai and Riyadh, including the $667m HUMAIN Infra financing for Saudi AI data centres. Sharjah’s plan extends that activity to the UAE’s east coast, where a Gulf of Oman location sits outside the Strait of Hormuz.
Power is a key constraint on any large data centre, which is why the masterplan reserves land for two power stations rather than relying only on the existing grid. Free zone status adds the usual UAE incentives for AI investment, including 100 per cent foreign ownership, full repatriation of profits and capital, and exemptions from customs duty and corporate tax, according to AGBI.
The announcement also lands in a week when the IMF moved its UAE growth forecast back into positive territory, projecting 0.2 per cent growth in 2026 and 7.3 per cent in 2027 as disruption from the Iran war eases.
What happens next
Masterplan approval moves the Sharjah data centre complex from decree to design, but the next steps have yet to be announced. Those include appointing a developer, releasing plots, securing power supply agreements and setting a construction schedule.
Investors will watch for an SCTA tender or a follow-on announcement with Khaznah Sharjah, and for any disclosure of the capital cost of the two power stations. The official masterplan announcement is available from the Emirates News Agency (WAM).