HUMAIN Infra financing: $667m for Saudi AI data centres
HUMAIN Infra financing deals worth SAR2.5bn ($667m) will fund GPUs and power infrastructure for Saudi AI data centres with up to 1GW of IT capacity.

Saudi AI company HUMAIN and the National Infrastructure Fund (Infra) have signed HUMAIN Infra financing agreements worth up to SAR2.5 billion ($667 million) to fund GPUs and power infrastructure for AI data centres in the Kingdom.
The two facilities were signed in Riyadh on 8 November, announced on 9 November, and are the first transactions under Infra’s AI Data Centre Financing Program. Infra is the Kingdom’s development financing arm for infrastructure and is part of the National Development Fund, while HUMAIN is the artificial intelligence company backed by the Public Investment Fund (PIF).
The agreements follow a framework announced by the two parties at the World Economic Forum in Davos in January 2026, which set out non-binding terms for up to SAR4.5 billion ($1.2 billion) of financing for AI and digital infrastructure projects in Saudi Arabia.
How the HUMAIN Infra financing is split
The first facility, of up to SAR1.1 billion ($293.3 million), will fund the procurement and deployment of graphics processing units representing roughly 25 megawatts of IT load. GPUs are the specialised chips used to train and run large AI models, and securing them has become one of the biggest cost items for any data centre developer.
The second facility, of up to SAR1.4 billion ($373.3 million), is earmarked for substations, electricity transmission infrastructure and grid connections serving HUMAIN’s data centres. Infra said the power build-out is designed to support future data centre IT loads of up to 1 gigawatt.
The signing took place in the presence of PIF Governor Yasir Al-Rumayyan, Minister of Economy and Planning and Infra Chairman Faisal bin Fadhil Alibrahim, and National Development Fund Governor Abdulaziz Alarifi.
Eng. Esmail Alsallom, Chief Executive Officer of Infra, said: “Through these agreements, we aim to unlock investment well beyond Infra’s own commitment.” Tareq Amin, Chief Executive Officer of HUMAIN, said that “AI infrastructure is becoming foundational to the next generation of computing”.
HUMAIN’s wider data centre build-out
HUMAIN was set up by PIF in May 2025 to build a full stack of AI capabilities, from data centres and cloud platforms to Arabic-language models. It has since signed partnerships with chip and technology groups including NVIDIA, AMD, Qualcomm and Cisco, and is targeting 3 gigawatts of AI data centre capacity by 2030.
Part of its construction is being handled by Riyadh-based Al Moammar Information Systems (MIS), which signed a design-and-build contract with HUMAIN in March 2026. The project’s planned capacity was later raised from 50 megawatts to 250 megawatts, and MIS has received several work orders under the expanded agreement since October.
Ownership of the company also changed earlier this month. On 1 November, PIF and Saudi Aramco completed a transaction that gave the oil major a 49 per cent stake in HUMAIN for SAR9.9 billion ($2.6 billion) in cash plus AI, computing and digital assets, bringing in a second state-linked shareholder with substantial in-house computing needs. PIF retains 51 per cent.
Why the deal matters for Gulf AI investors
Gulf governments and state-backed companies have announced AI capacity plans measured in gigawatts, but relatively little of that pipeline has so far been financed on commercial terms. Lenders typically want signed customer contracts, clear allocation of construction risk and secured power before they commit, and AI data centres are still a young asset class for Gulf banks.
Infra’s entry as a lender therefore matters less for the size of the cheque than for what it signals. A state development financier funding GPUs and grid connections can make it easier for commercial banks, hyperscalers and institutional investors to follow, which is the outcome Infra says it is targeting.
The deals also separate two risks that are often bundled together in AI infrastructure projects. Financing the chips and financing the power are distinct problems, and funding them under separate facilities reflects the fact that substations and grid connections must be in place before any GPUs can be switched on.
Also Read: Oman AI data centre: Mubbadrah leads $3bn, 400MW plan
What happens next
HUMAIN is also preparing a dedicated data centre investment fund. Bloomberg reported in September that the company plans to raise an initial $2.5 billion from domestic and international investors through a vehicle managed by BSF Capital, the investment arm of Banque Saudi Fransi, subject to approval from the Capital Market Authority. According to that report, the fund would back the 250 megawatts of capacity being built with MIS, which could eventually grow to as much as 1 gigawatt.
Saudi media described the HUMAIN Infra financing agreements as the first phase of the January framework. Further drawdowns under the SAR4.5 billion framework, and the first customer offtake contracts for HUMAIN’s new capacity, will be the next signals of whether Saudi Arabia can turn its AI ambitions into bankable assets. Details of the January framework are available in the joint HUMAIN and Infra announcement.